NEW CUMBERLAND -- A decision on proposed improvements to the baseball and softball fields at Oak Glen High School will have to wait at least a couple more weeks, following Monday's meeting of the Hancock County Board of Education.

Superintendent Dawn Petrovich noted discussions on the possibility of moving forward with the project have been held in recent months, with plans calling for the installation of new turf and lighting at the existing fields.

"The board had voted to get quotes," she said, explaining prices given to the board equated to $3.1 million.

Joe Campinelli, chief financial officer for the school district, pointed out the estimates called for $2.5 million for the turf, and $600,000 for the new lighting.

"This uses the existing fencing and the dugouts are the same," Campinelli said, explaining the quotes were being considered a "worst-case" scenario, and he anticipated opportunities for savings.

Campinelli said a $375,000 down payment already had been budgeted, with plans to put together a seven-year financing plan at a cost of $477,000 per year.

Campinelli also noted the Oak Glen project wouldn't begin until after work on the new softball and baseball fields at Weir High are completed.

Board member Larry Shaw cited the importance of being able to complete the project either before the next softball season begins, or waiting until it is finished.

"Oak Glen does not have other fields they can go to," he said.

Despite the recommendation from Petrovich, and a proposed funding package, board President Chris Gillette asked to table to measure, saying he wanted to see more information before making a decision, especially as it concerns the project's budget.

"I haven't seen any drawings on it," he said. "I basically got a hand-written note."

Board member Gerard Spencer also expressed concerns on what funds would be available, claiming potential deficits for the ongoing Weir High projects, which Campinelli, earlier in the meeting, said would be covered primarily through supplemental funds, budget transfers and carryovers for the field projects, and budgeting the necessary funds over the next two years for the physical education expansion.

Board Vice President Ed Fields, though, urged the board not to delay the project too long, saying construction crews might take on other projects.

"If we hold this off for a month, or two months, it puts us further down the list," he said.

As it was tabled, the proposal will appear again on the board's next regular meeting agenda.