Wastewater treatment plant expansion continues toward the finish line
WEIRTON – While substantially complete, the Weirton Sanitary Board is hoping to get a few final “wish list” items as part of the project expanding the capacity of the city's wastewater treatment plant. Jesse Alden, project manager from Thrasher Engineering, reported during the board's meeting Thursday, the project to expand the treatment plant to a capacity of 8 million gallons per day, stands at a 99.7 percent completion, based on the expenditures of the $38,572,670.37 contract with Triton Construction. “We're waiting on some additional proposals from Triton to work through ...